The City of Mysore is developing
at a fast pace, owing to the presence and fresh arrival of number
of new industries, educational institutions and also owing to
world famous tourist spots in and around the City. On account
of the fast development of the city, vehicular traffic has also
increased manifold, thereby causing traffic congestion in the
city. To decongest the city & to have an easy access to the
various new layouts developed by MUDA and to connect major roads
of the city to a single arterial road the Mysore Urban Development
Authority proposed the Outer Ring Road. Though this proposal was
mooted long back, it could not be implemented owing to financial
constraints. However, the MUDA with the financial assistance of
Asian Development Bank in coordination with Karnataka Urban Infrastructure
Development Finance Corporation has taken up this project and
has completed it successfully.
The total length of outer ring road is 32.357 KM, with a width
of 45 Mtr all along having a provision of 4 lanes. Out of.32 357
K. M., 24.872 K. M., runs on the western side and 7.485 K. M.,
runs on the eastern side of the city. Due to financial constraint
only 2 lane width of road is constructed on western side of the
ring road; since 4 lane road was formed during the construction
of sites and Services, this was continued and completed as four
lanes in the eastern wing of the ring road.
The
total cost of the project was Rs. 50,14,43,027=00
The ORR is completed in all respects and opened for traffic during
October 2004 and the vehicles are moving on the entire ORR. Further
following efforts have been taken up by MUDA for the improvement
of ORR i.e.,
| 1. |
Complete plantation on ORR under
the project called GBMORR (Green and Beautiful Mysore Outer
Ring Road) has been taken up with the financial assistance
from WeP Peripherals, Bangalore at cost of Rs. 24.00 lakhs,
till now around 100% of ORR has been covered by tree plantation
with various species of trees. Forest department is executing
the work. |
| 2. |
9.5 K. M., of O.R.R is still to be constructed
on the eastern portion of the city, where the land acquisition
is under progress and will be completed soon. |
| 3. |
Complete lighting of ORR is being taken up. |
| 4. |
Destination boards are being put on the ORR
along with traffic aid equipments. |