4. What is the time taken for the Authority to give the relevant documents to the successful bidder?
 
 
The total number days taken is 28 days. The breakup is as follows,

Report from the Accounts Department                            2 Days
Auction Certificate                                                          2 Days
Ledger Notification                                                         2 Days

Report from Tahasildar                                                    2 Days

Report from Assistant Secretary                                      1 Day
Report from Secretary                                                     1 Day

Order from the Commissioner                                          2 Days
Dispatch                                                                          1 Days

Report from the Engineering Department                        10 Days

Report from the Accounts Department                             2 Days
Possession Certificate                                                      2 Days

Report from the Accounts Department                             1 Day

Total                                                                             28 Days
 